State extends Concord wastewater-treatment energy-efficiency grant deadline to Aug. 31
New Hampshire has extended the completion deadline for energy-efficiency improvements at Concord’s wastewater treatment facility to Aug. 31, 2026, under a no-cost amendment listed on the state’s Jan. 28 Governor and Council agenda.
The amendment changes the project’s prior completion date of Feb. 28, 2026. The state record identifies the work as a grant amendment for the City of Concord’s wastewater-treatment energy-efficiency project.
Deadline moves by six months
The revised deadline gives the city until Aug. 31 to complete the grant-funded work. The agenda describes the amendment itself as having a stated cost of $0 and says the project is funded with 100% federal funds.
The record does not give a reason for the extension. It also does not state the total value of the underlying grant or the share of work that has been completed.
As a result, the state action establishes a revised completion milestone rather than confirming that the energy-efficiency improvements are finished. No energy-use or emissions-savings estimate is provided in the agenda record.
State environmental agency administers grant
The New Hampshire Department of Environmental Services is identified as the administering agency for the Concord grant. The item concerns a public wastewater facility, where the approved work is specifically described as energy-efficiency improvements.
The amendment originated from a grant that had been approved for Concord on March 22, 2023, according to the state agenda. The Jan. 28 action modifies the completion schedule for that earlier award without a stated additional cost for the amendment.
For Concord, the Aug. 31 date is the next documented deadline in the state record for this environmental-infrastructure project. The available agenda material does not identify further construction milestones, a new grant amount, or additional conditions attached to the extension.
What the action does and does not establish
The Governor and Council agenda action approves a deadline change for a federally funded project; it is not a finding about current facility performance. The record does not quantify expected reductions in energy use or emissions, and it does not identify a cause for moving the deadline.
The extension nevertheless keeps the Concord project on an active state-administered grant schedule through the end of August. The city’s wastewater-treatment facility remains the specifically named site for the energy-efficiency work covered by the amendment.
Sources
- January 28, 2026 Governor and Council Agenda, New Hampshire Secretary of State